Change control procedures MCQs With Answer is designed to help M.Pharm students master the critical concepts of formal change management in pharmaceutical quality systems. This blog features focused multiple-choice questions that probe regulatory expectations, risk-based assessments, documentation practices, validation impacts, and the role of cross-functional Change Control Boards. Questions cover real-world scenarios such as emergency changes, supplier modifications, computerized system updates, and regulatory submission pathways to build practical decision-making skills. Each MCQ includes clear options and correct answers to reinforce learning and prepare students for university exams and practical industry responsibilities in QC & QA functions. Use these questions for self-assessment and deeper topic revision.
Q1. What best describes a formal change control system in pharmaceutical manufacturing?
- A reactive process used only when deviations occur
- A formal documented system to propose, assess, approve, implement and review changes
- An informal communication between departments for small adjustments
- A procedure limited to updating batch documentation
Correct Answer: A formal documented system to propose, assess, approve, implement and review changes
Q2. What is the correct first step when initiating a change control?
- Implement the change immediately
- Raise a change request or change initiation form
- Perform full validation studies
- Notify regulatory authority
Correct Answer: Raise a change request or change initiation form
Q3. Which group is primarily responsible for reviewing and approving changes?
- Individual department head where change originates
- Change Control Board or cross-functional team including QA
- External consultant only
- Production operators implementing the change
Correct Answer: Change Control Board or cross-functional team including QA
Q4. Which risk assessment tool is commonly used to evaluate the impact of a proposed change?
- HACCP exclusively
- Failure Mode and Effects Analysis (FMEA)
- Random sampling without analysis
- Only historical trend review
Correct Answer: Failure Mode and Effects Analysis (FMEA)
Q5. Which type of change typically requires prior regulatory submission or approval?
- Administrative changes with no quality impact
- Minor editorial changes to label text
- Major changes that could affect product quality, safety, or efficacy
- Internal SOP format updates only
Correct Answer: Major changes that could affect product quality, safety, or efficacy
Q6. How should an emergency change that affects product quality be handled?
- Implemented immediately without documentation
- Implemented with immediate containment, documented, and followed by retrospective assessment and approval
- Ignored until the next scheduled Change Control Board meeting
- Only communicated verbally to production staff
Correct Answer: Implemented with immediate containment, documented, and followed by retrospective assessment and approval
Q7. What is the purpose of an effectiveness check after implementing a change?
- To close the change control without further review
- To verify the change achieved the intended result and did not introduce new risks
- To notify suppliers only
- To reduce documentation requirements
Correct Answer: To verify the change achieved the intended result and did not introduce new risks
Q8. Which document should detail the stepwise procedure for managing changes in a pharmaceutical site?
- Batch production record
- Change control standard operating procedure (SOP)
- Marketing brochure
- Individual operator notes
Correct Answer: Change control standard operating procedure (SOP)
Q9. On what basis are changes typically classified as minor or major?
- Based solely on cost impact
- Based on the color of labels affected
- Based on potential impact on product quality, safety, efficacy, and regulatory compliance
- Based only on the department proposing the change
Correct Answer: Based on potential impact on product quality, safety, efficacy, and regulatory compliance
Q10. When is revalidation or requalification usually required after a change?
- Only when the change is cosmetic
- When the change affects a previously validated process, equipment, or critical parameter
- Never required for supplier changes
- Only if the regulatory authority requests it
Correct Answer: When the change affects a previously validated process, equipment, or critical parameter
Q11. Who should perform the impact assessment for a proposed change?
- The initiating operator alone
- A cross-functional team including QA, QC, production, engineering and regulatory as required
- An external auditor only
- Sales department only
Correct Answer: A cross-functional team including QA, QC, production, engineering and regulatory as required
Q12. How are deviations, CAPA and change control related?
- They are unrelated quality systems
- Changes may be initiated as corrective actions from deviations or CAPA investigations
- CAPA replaces the need for change control
- Deviations always negate the need for change control
Correct Answer: Changes may be initiated as corrective actions from deviations or CAPA investigations
Q13. Which metric is useful to monitor the performance of a change control system?
- Number of printer cartridges used
- Average cycle time from change request to closure and percent of emergency changes
- Number of coffee breaks during meetings
- Only the number of changes raised without timing
Correct Answer: Average cycle time from change request to closure and percent of emergency changes
Q14. What special considerations apply when changing computerized systems used for GMP activities?
- No validation or documentation is needed for software
- Changes require computerized system validation and adherence to GAMP principles plus documented testing
- Only the IT department needs to be informed
- Backups alone are sufficient
Correct Answer: Changes require computerized system validation and adherence to GAMP principles plus documented testing
Q15. When a supplier changes a raw material specification or manufacturer, the appropriate action is to:
- Accept all deliveries without review
- Manage via change control with supplier assessment, potential requalification, and impact evaluation
- Only change the PO terms
- Ignore until a product failure occurs
Correct Answer: Manage via change control with supplier assessment, potential requalification, and impact evaluation
Q16. If a formulation component is modified, what must typically be performed?
- Immediate product launch without testing
- Stability studies, analytical method evaluation, and possible clinical/regulatory assessment depending on impact
- Only update the ingredient name on label
- Only notify marketing
Correct Answer: Stability studies, analytical method evaluation, and possible clinical/regulatory assessment depending on impact
Q17. The FDA CBE-30 (Changes Being Effected in 30 days) pathway allows what?
- Immediate permanent change without submission
- Implementation of certain changes 30 days after submission unless FDA notifies otherwise
- Automatic denial of any change
- Changes must wait one year for approval
Correct Answer: Implementation of certain changes 30 days after submission unless FDA notifies otherwise
Q18. Retrospective (post-implementation) change control approval is acceptable when:
- It is the routine approach for all changes
- Only used in justified emergency circumstances with full documentation, review and corrective actions
- No documentation is provided
- Regulators always prefer retrospective change control
Correct Answer: Only used in justified emergency circumstances with full documentation, review and corrective actions
Q19. A typical Change Control Board should include which members?
- Only the plant manager
- Representatives from QA, QC, Production, Engineering, Regulatory Affairs and R&D as applicable
- Only external vendors
- Only marketing and sales
Correct Answer: Representatives from QA, QC, Production, Engineering, Regulatory Affairs and R&D as applicable
Q20. Can a product batch be released to market based on processes changed but not yet approved by change control?
- Yes, if production staff approve it informally
- No, batches impacted by unapproved changes should not be released until change control approval and necessary validation are complete
- Yes, if the change is documented in a notebook
- Only if the change was verbal
Correct Answer: No, batches impacted by unapproved changes should not be released until change control approval and necessary validation are complete

I am a Registered Pharmacist under the Pharmacy Act, 1948, and the founder of PharmacyFreak.com. I hold a Bachelor of Pharmacy degree from Rungta College of Pharmaceutical Science and Research. With a strong academic foundation and practical knowledge, I am committed to providing accurate, easy-to-understand content to support pharmacy students and professionals. My aim is to make complex pharmaceutical concepts accessible and useful for real-world application.